PROJECTS in which Robert BUESS was involved

2016 – 2020    Société Saoura Ciment, Algeria

Greenfield: Cement plant 1.2 mio t/y : EPC project. Design engineering approval, erection, commissioning and plant personnel formation supervision.

2017 – 2021    Société des Ciments de Sigus, Algeria

Greenfield: Cement plant 2.2 mio t/y : EPC project. Design engineering approval, erection and commissioning supervision.

2015                 Algeria, CEVITAL Minerals Spa., study of basic engineering and call for tenders for a new cement plant 2 times 6'000 tpd clinker, at El Khroub.

2015                 Mongolia, Senj Sant Cement plant, design study and monitoring of the project on behalf of the lenders (EBRD).

2014 - 2015     Nigeria, Giant Cement Company Ltd, feasibility study for a new cement plant (6’250 tpd clinker), including a power plant in the State of Cross River.

2014 - 2015     Nigeria, International Cement Company Ltd.,  feasibility study, call for tenders for a new cement plant of 3'600 tpd clinker including power plant in the state of Ogun.

2012 - 2015     Tanzania, Tanga Cement Company Limited, study design and monitoring of the project on behalf of the lenders.

2011 - 2012     Benin, project management of the new cement plant of Benin (NoCiBe) of  3'600 tpd clinker including power plant. Complete engineering, including feasibility study, detail engineering, call for tenders, negotiation of contracts, supervision of the project execution and commissioning.

2011 - 2012     Nigeria, United Cement Company of Nigeria Ltd. (Unicem), review of the civil engineering and the project management of a primary crusher department.

2010                 Nigeria, Ebonyi Cement Company :  feasibility study of a new cement plant.

2010                 Switzerland, cement Vigier (Group of cements Vicat): Audit of the civil engineering and supervision of construction of a rail loading facility for bulk cement.

2009 - 2010     Namibia, Ohorongo Cement (Group Schwenk Zement), new cement plant of 2'800 tpd clinker: design study and monitoring of the project on behalf of the lenders.

2007 - 2010     Morocco, cement factory in El Jadida, new cement plant of 3'600 tpd clinker, complete engineering, including feasibility study, geology, engineering, call for tenders and contracts.

2007 - 2010     Omega, south of Europe, 5’000 tpd clinker, feasibility study and engineering for an EPC project.

2009 - 2010     Senegal, Les Ciments du Sahel, expansion with achievement of a line of 3'600 tpd of clinker. Project with complete engineering, including feasibility study, basic engineering, call for tenders, contract, supervision of the project execution including commissioning.

2008 - 2009     Marwar Mundwar, Ambuja Cement Ltd., India, greenfield project of 7'000 tpd clinker, feasibility study.

2008 - 2009     Kymore, Ambuja Cement Ltd., India, expansion of 7'000 tpd clinker, feasibility study.

2008 - 2009     Chanda, Asociated Cement Ltd. Ltd, India, expansion of 7'000 tpd clinker, feasibility study.                

2008 - 2009     Missisauga, Canada, milling of slag cement 500'000 tpy, feasibility study.

2008 - 2009     Tuban, Indonesia, greenfield plant, 4’000 tpd clinker, feasibility study, call for tenders based on a turnkey project.

2007 - 2009     Ambuja Cement Ltd., India  grinding unit Bargahr (Patna, Bihar, Capital), grinding unit of clinker with a capacity of 1.0 mil tpa.

2007 - 2010     Novi Popovac, Serbia, increase in the production of 2’400 tpd clinker to 3’000 tpd clinker, execution of the project in multi package.            

2007 - 2009     Phillipines, new cement plant, 6’000 tpd clinker, feasibility study. 

2007 - 2009      Kembla port, Australia, grinding station, feasibility study.

2007 - 2009     India - grinding unit Sanand Ambuja Cement Ltd. (Ahmedabad, Gujarat, Capital),  grinding unit of clinker with a capacity of 1.5 mil tpa. 

2007 - 2009     New cement plant at Antoing, Belgium of 2.5 Mio tpa clinker.

2007 - 2009     Weston, New Zealand, new cement plant of 2'500 tpd clinker, feasibility study.

2007 - 2009     Gladstone, Australia, expansion 6’000 tpd of clinker, feasibility study.                                              

2007 - 2009     Argo, Romania, new cement plant of 4'000 tpd of clinker, feasibility study.

2007 - 2009     Campo Godoy, Colombia, new cement plant 4’000 tpd of clinker, feasibility study.                             

2007 - 2009     Omega, Spain, new cement plant of 4’500 tpd of clinker, feasibility study.

2007 - 2009     Calabar, Nigeria, new cement plant of 5'500 tpd of clinker, feasibility study.

2007 - 2009     Guayaquil, Ecuador, Center of grinding, feasibility study, call for tenders and the execution of the project on a turnkey approach.

2007 - 2009     Hermosillo, Cementos Apasco, Mexico, new cement plant of 3’500 tpd of clinker, call for tenders and project execution including site supervision.

2007 - 2009     San Juan, Cementos Progreso, Guatemala, new cement plant of 4'500 tpd of clinker, call for tenders and project execution.

2007 - 2009     Afrisam Dudfield, South Africa, kiln number 4 of 6'000 tpd of clinker, kiln and storage of clinker, feasibility study.

2007 - 2009     Quebrancha / Tucan, Cemento Panama City, Panama, grinding station 75 tph, feasibility study, call for tenders and the execution of the project based on a multi package approach as project manager including site supervision.

2007 - 2009     Tanga, Tanzania, AfriSam, a new cement mill in the existing facilities, feasibility study, call for tenders and the execution of projects based on a turnkey approach, acting as project manager including site supervision

2007 - 2008     New Wadi, Asociated Cement Ltd. Ltd., India, increase in capacity of clinker production of 7'100 to 12'500 tpd of clinker at Wadi, and new grinding stations to Bellary and Kolar

2007 - 2008     Port Daniels, Canada, New Factory of Greenfield, 3000 tpd of clinker, feasibility study

2006 - 2009     Tula, Cement Group Alpha, Russia, greenfield plant of 4.3 mio t cement, feasibility study, call for tenders and the execution of the project based on an EPC approach. 

2008 - 2009     Fes, Morocco, upgrade to 2’800 tpd of clinker, feasibility study, call for tenders and the execution of the project, including the site supervision 

2006 - 2009     Campulung , Romania, expansion, 4’000 of clinker, semi turn-key approach, feasibility study, call for tenders and the execution of the project, including the site supervision       

2006 - 2009     Pillango, Hungary, new cement plant of 4’000 tpd of clinker, feasibility study

2006 - 2008     Bathapara, Associated Cement Ltd. Ltd., India, the new kiln with a capacity of 7’000 tpd clinker; 1x33 MW CPP, project execution, including the site supervision

2006 - 2008     Gujarat Ambuja, India, new cement plant of 7’000 tpd of clinker

2006 - 2008     Roodepoort, South Africa, cement mill number 8, feasibility study, call for tenders and the execution of the project based on a semi turn-key approach.

2006 - 2008     Malagueno, Cementos Minetti, Argentina, restart of existing line of existing kiln, feasibility study.       

2006 - 2007     Koromacno, Serbia, upgrade of the cement grinding with a roller press, multi package approach, feasibility study and call for tenders.

2005 - 2009     Shurovo, Alpha Cement, Russia, 5’500 tpd clinker, expansion, feasibility study, call for tenders and execution of the project including the site supervision

2005 - 2009     Volsk, Red October, Alpha Cement, Russia, replacement of existing lines of 4.0 million of tpa at the existing site, feasibility study, call for tenders

2005 - 2007     Kashan, Iran, new cement plant of 3’500 tpd clinker of clinker, assistance to project management

2005 - 2007     Atlacim / Settat, Morocco, new cement plant of 4’000 tpd clinker, feasibility study, call for tenders and the execution of project based on a semi turnkey approach, acting as project manager including site supervision

2005 - 2007     Rohoznik, Slovakia, upgrade the capacity of the kiln to 4’000 tpd of clinker, feasibility study, call for tenders and the execution of the project as project manager including site supervision                                                        

2005 - 2006     Macuspana, Grupo Apasco, Mexico, cement grinding upgrade, feasibility study, call for tenders and the execution of the project                                                        

2004 - 2009     Hon Chong, Morning Star Cement, Vietnam, expansion of 9’000 tpd clinker of clinker, feasibility study                                     

2004 - 2008     The Beli Izvor, Bulgaria, upgrade of the kiln of 1’400 to 3’300 tpd of clinker, feasibility study, call for tenders and the execution of project based on a turnkey approach, acting as project manager including site supervision               

2004 - 2007     Cartago, Costa Rica, expansion of 3’000 tpd of clinker, feasibility study, call for tenders and the execution of project based on a turnkey approach, acting as project manager including site supervision                                                  

2004 - 2007     Morano, Italy, upgrade of a cement grinding station, execution of the project       

2004 - 2006     The Asociated Cement Ltd. Bargarh, India, increase the capacity of cement 1.03 to 2.14 tpa., call for tenders and the execution of the project on a multi package approach including the site supervision                                                        

2004 - 2006     Faraz Faraz Firouzkuh Firozkouh, Iran Cement Co., new cement plant, execution of the project as project manager including site supervision                                                        

2004 - 2005      Ibity, Madagascar, replacement of existing vertical kilns to latest technology of 1’200 tpd of clinker, feasibility study                                                        

2003 - 2009     Huaxin Cement, China, the assistance to management in several projects of complete cement plants  (Yangxin, Yangxin, HB; Yichang Yidu, HB; Yibin (Yunnan), Yunnan; Xiangfan, Xiangfan, HB; Chongqing, Chongqing and Huangshi, Huangshi, HB) and projects of grinding stations (Wugang, Wuhan, HB; Nantong, Nantong, js; Hongqi, Huangshi, HB; Xiantao, Xiantao, HB; Ergang, Erzhou, HB; Huangshi; Yichang; Yangxin; Yunnan; Xiangfan and Chongqing)                                                        

2003 - 2008     Buraydah, Qassim Cement, Saudi Arabia, expansion, 4’500 tpd of clinker, call for tenders and the execution of the project on a turnkey approach, acting as project manager including site supervision

2003 - 2008     St. Geneviève, USA, new cement plant, 12'000 tpd of clinker, feasibility study, call for tenders and the execution of projects based on a semi turnkey approach.

2003 - 2005     Merone, Italy, cement mill No. 7, vertical mill TYPE MPS 4250 BC of Gebr. PFEIFFER AG, feasibility study, call for tender and execution of the project 

2003 - 2005     Thi Vai, Vietnam, new grinding station greenfield, feasibility study, call for tenders, the execution of the project and the assistance to the management. 

2003 - 2004     Chekka, Lebanon, increase of cement grinding 2.2 mio. tpa, feasibility study and call for tenders.                                              

2003 - 2004     Mejillones, Chile, increase of the cement grinding, feasibility study and call for tenders.

2003 - 2004     Gladstone, Australia, new grinding station, feasibility study, call for tenders and the execution of projects based on a

turnkey approach, acting as project manager including site supervision.

2003 - 2004     Palavi, Sri Lanka, new grinding station, feasibility study, call for tenders and the execution of projects based on a turnkey approach, acting as project manager including site supervision 

2002 - 2007     El Soukhna, ECC, Egypt, Greenfield, 4 times 5’000 tpd of clinker, call for tenders and the execution of projects based on a turnkey approach, acting as project manager including site supervision.  

2002 - 2005     Alesd, Romania, rehabilitation of the entire plant, 3’000 tpd clinker, multi package approach, call for tenders and the execution of project, acting as project manager including site supervision  

2002 - 2004     Carboneras, Spain, new cement mill using a vertical mill type Loesche Mill (VRM), multi package approach, call for tenders and project management. 

2002 - 2004     Sharr, Kosovo, full rehabilitation of the Factory, 2’300 tpd of clinker, calls for tenders and the execution of projects based on a multi package approach, acting as project manager including site supervision.

2002 - 2004     Ras El Ma, Morocco expansion of the capacity of cement grinding using a new vertical mill type Loesche Mill (VRM), feasibility study and call for tenders on a turnkey approach with Kawasaki and execution of the project.

2002 - 2004     Dunkerque, France, greenfield cement grinding with vertical mill type Loesche, multi package approach and  assistance to the execution of the project.                                           